Garage E Surface Lot
A new surface parking lot will be added next to Garage E by paving the adjacent grassy area; see map here for reference. The existing parking spaces will also be upgraded during this project.
Timeline (dates subject to change)
- Start Date: June 2, 2025
- Target Completion Date: July 21, 2025
- Garage E Surface grass lot will be closed during construction.
Paving Lot H4A
The H4A gravel lot in Greek Park will be paved in June and July.
Timeline (dates subject to change)
- Start Date: June 9, 2025
- Target Completion Date: July 27, 2025
- Lot H4A will be closed as of June 4, 2025 to allow equipment to prep for construction.
Any project updates will be posted to this page.